Turbine Component Delivery

Turbine Component Delivery

Major milestone achieve ahead of schedule

Early this morning we received the first turbine components to the Moanvane project. They left Galway port in the early hours and arrived to site just after first light. With the exception of a slight delay due to an abandoned vehicle in Galway, the deliveries arrived to the site without incident.

Huge credit to Adman, our civil contractor, for delivering the components ahead of schedule to accommodate early deliveries. Also, credit to our HSSE team for assisting Nordex with the PSCS takeover.

Daily deliveries are planned for the next 7 to 8 weeks with installation to commence end of July / early August.