Public Road – Grid Route & Connection

Public Road – Grid Route & Connection

Trenching works will be commencing in February ’23

The project is at the stage where the grid connection phase will commence shortly. These works consist of the trenching, ducting, cabling and reinstatement of approximately 10km of grid infrastructure predominantly along Continue reading

Wind Farm Update

Wind Farm Update

Works completed to date

During the last quarter of 2022 public road-enabling works have been carried out and completed, while the substation platform has been constructed. In addition, the site roads associated with the project as well as all turbine Continue reading

Traffic Management Updates

Traffic Management Updates

A breakdown of the work areas and dates agreed with Offaly County Council are listed below:

September 12th – 14th: Location R-420 – 5 Killellery / Curragh

September 14th  – 16th: Location R420 – Continue reading

Construction Begins on Moanvane Wind Farm

Construction Begins on Moanvane Wind Farm

Statkraft has confirmed that it has recently begun construction on Moanvane Wind Farm, located in Co. Offaly, between the villages of Cloneygowan and Walsh Island. 

Moanvane Wind Farm is a 12 turbine, 57.6MW project that will deliver a significant Continue reading

Wind Farm Update

Wind Farm Update

As part of the development process of the permitted Moanvane Wind Farm, we recently informed residents, by way of a letter drop in the local area, that we will soon be starting the initial stages of construction.

This renewable energy Continue reading

Community Benefits Fund

Community Benefits Fund

The Community Benefit Fund for Moanvane is a significant fund, which will bring in the region of €300,000 per year to the local community, which adds up to €4,500,000 over the lifetime of the project.

This fund has a lot Continue reading

Preparatory Works

Preparatory Works

In order to facilitate a potential start of construction later this year, some preparatory works will begin on site (w/b 21 February 2022).

These preparatory works will include hedge trimming/cutting, and will take place before the bird nesting season which Continue reading

Planned Community Engagement

Planned Community Engagement

In advance of any construction starting, the following will be undertaken:

  • Everyone within a 1km radius of the site will be notified and kept informed of any planned works
  • A Community Liaison Officer (CLO) will be appointed as a dedicated Continue reading