Concrete Pours

Concrete Pours

Scheduled to start week commencing 6th Feb ’23

Generally, there is no activity on the site outside the hours of 7:00am – 7:00pm.  However, as the project progresses, there are a number of isolated occasions that the site will have to work outside of these hours.

These occasions are on the days of the Turbine Foundation Concrete Pours.

  • Works consist of approx. ONE pour per week for 12 weeks
    • It will be necessary to start these works to start at 4am on the day to allow a full pour to be completed within the day.
  • Concrete trucks will be delivering concrete to the site using the L1013 from the R420

    Should you have any queries or require any further information, please contact the project Community Liaison officer, Suzanne O’Leary on
    Phone: 057 937 9073

    We would like to apologise for any inconvenience in advance.