Notifications

Road Closure Notice for December

Road Closure Notice for December

The following road closures will take place to facilitate necessary works for the project. Local access will be maintained where possible at all times. It is necessary to carry out these works under road closures, however, Continue reading

Moanvane Wind Farm Project Works Update

Moanvane Wind Farm Project Works Update

Project Works Update

  • Duct installation works are now complete on the public roads.

Component Delivery Update

  • Main component deliveries are ongoing.

Turbine Install Update

  • Erection of turbines are planned to commence in Late July and continue over a 3-month window. Continue reading
Turbine Component Delivery

Turbine Component Delivery

Major milestone achieve ahead of schedule

Early this morning we received the first turbine components to the Moanvane project. They left Galway port in the early hours and arrived to site just after first light. With the exception of a Continue reading

Traffic Management Update

Traffic Management Update

  • There will be an Abnormal Load trial run in the early hours of Tuesday 6th June
  • The trial run will be escorted by An Garda Siochána who may stop traffic on the L1013 (R420 junction to Moanvane Site Entrance) Continue reading
Road Closure Notice No.3 – L1013

Road Closure Notice No.3 – L1013

L1013 : May – June 2023

  • These closures are scheduled for May/June 2023 to Commence Cable Route
  • Local access will be maintained at all times. It is necessary to carry out these works under road closures, however, we will work proactively to minimise disruption Continue reading
Road Closure Notice No. 2 – L5042

Road Closure Notice No. 2 – L5042

L5042 : Mid-March ’23

  • These closures are scheduled for mid March 2023
  • Local access will be maintained at all times. It is necessary to carry out these works under road closures, however, we will work proactively to minimise disruption during this time.

To view the full road Continue reading

Concrete Pours

Concrete Pours

Scheduled to start week commencing 6th Feb ’23

Generally, there is no activity on the site outside the hours of 7:00am – 7:00pm.  However, as the project progresses, there are a number of isolated occasions that the site will have Continue reading

Road Closure Notice No. 1 – L1014

Road Closure Notice No. 1 – L1014

L1014 – February ’23

  • The works are scheduled to commence in late February 2023
  • Local access will be maintained and at all times. It is necessary to carry out these works under road closures, however, we will work proactively to Continue reading